Project Name

 Start

End

 Areas Impacted

HVAC Replacement

HVAC Replacement

HVAC Replacement

HVAC Replacement

HVAC Replacement 

10-16-17

11-3-17

11-20-17

11-20-17

11-27-17

12-11-17

12-18-17 

11-03-17

11-10-17

12-1-17

12-8-17

12-15-17

12-22-17

12-29-17 

Learning Resource Center

Stadium

IAC Building A

CDC (West Portable)

CDC (East Portable)

Baseball Field House

Plant Science 

Power Loop Upgrade (Phase 1)  11-27-17  12-18-17

 P10 parking lot will be blocked off for contractors to store their equipment.  Fencing will be erected at work areas for the protection of Students/Staff/Faculty.  Project will include concrete cutting but will be limited to times with low student activity as to avoid any disturbance.

 Power Loop Upgrade (Phase 2) 12-28-17   1-15-18  Project will continue with work at the front of Lesher Bldg, past Administration Bldg, to the Gym routing between the Veteran's Resource Center and the Music Bldg.