The Science Building remodel project is now in its sixth month and progress remains on schedule. The exterior portion of the facility’s west addition is almost complete and the entire project is scheduled for completion in August. Among this month’s activities are completion of the roof, finishing of masonry work on the new, west addition, more interior framing, and other items. These photos show the masonry work on the west addition, the building windows, and the preparation of the roof.
|